Walnut Street Construction Update

Please note that Phase 1B will now start early MONDAY MORNING, instead of what was originally scheduled for Tuesday.

From Kevin Daeger, HWC Engineering....

* Paving at Madison Avenue was completed this afternoon and the project will move into phase 1B starting MONDAY MORNING (last update was that it would start Tuesday)

* The contractor will be adjusting traffic control measures in the early morning and Madison Avenue will be back open normally to the flow of traffic. Vehicles will not be permitted to turn right off of Madison Avenue into the downtown area but will be able to travel South to Buckeye Street or left to 5th Street.

*Jackson Street intersection will be completely shut down starting Monday morning 4-4-22.

* Also, the alleyway between Jackson Street and Madison Avenue will be closed to through traffic with barricades.

If you have questions or concerns throughout the duration of this project, you may use the following options:

Primary Contact: Kevin Daeger, HWC Engineering-email kdaeger@hwcengineering.com Cell# 812-592-5374;

Secondary Contact: Tim Hunt, HWC Engineering - email thunt@hwcengineering.com Cell# 502-648-7445.

Or, posting concerns online via our website at: https://www.northvernon-in.gov/citizen_request/index.php.

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS